Send us a recent JdVVNL bill on WhatsApp. We read three things from it: your monthly units, your sanctioned load, and your consumer category. That is enough to come back with an indicative system size and a price range before anyone travels to your house.
We read units rather than the rupee figure because tariff slabs change and units do not. A bill of ₹8,000 means different things in different slabs.
An engineer visits and spends time on the roof. Measured: usable shade-free area, shading through the day, roof structure and slab condition, existing earthing, meter position and the cable route from array to meter. You receive the findings in writing regardless of whether you proceed.
You get a fixed written quote listing the exact panel model and wattage, inverter make and model, structure specification and height, cable sizing, protection devices, the scope of civil work, the timeline and the payment schedule. Nothing verbal, nothing that changes after the advance.
We prepare and submit the net-metering application to Jodhpur Vidyut Vitran Nigam Limited and register your PM Surya Ghar application on the national portal. What we need from you at this stage:
This stage runs on DISCOM and portal timelines, not ours. We chase it; we do not control it.
Order of work on the roof:
A typical residential system is one to three days of on-site work depending on size, roof access and structure height.
JdVVNL inspects the installation and installs the bidirectional net meter. Once the meter is in and the connection is approved, the system goes live and export credit begins accruing.
Subsidy documentation is submitted with the commissioning report. You receive the handover pack: panel and inverter datasheets, warranty certificates, the single-line diagram, test records and the AMC schedule. Keep this pack — it is what a future buyer of your house will ask for.
Being straight about this saves everyone frustration. In practice the physical installation is rarely the bottleneck. Delays cluster in three places: DISCOM application processing and inspection scheduling, net-meter availability, and subsidy disbursal on the portal. All three are government-side. Any installer promising you a precise end-to-end date is promising you something they do not control — we give a realistic range instead, and tell you when something has slipped.